Downtown BG construction continues with concrete work

0

Concrete base repairs on the east side of Main Street is the focus this week as road construction
continues in downtown Bowling Green.
The contractor is breaking up the old concrete and will soon transition to removing those sections and
preparing the site for new concrete to be installed.
It is expected that by the end of next week, the intermediate course of asphalt will be placed. Once
complete, the contractor will begin making repairs to the sidewalks and isolated curb ramps on both
sides of Main Street.
Following the Black Swamp Arts Festival, work will move on to Wooster Street.
When the rehabilitation of Wooster Street begins, work will proceed in a similar pattern with concrete
base repairs followed by an intermediate course of asphalt being placed.
During this work, it is expected that Wooster Street will be closed in both directions due to the
narrower road width. This will allow concrete trucks to safely maneuver through the work zone.
After the entire project area has the intermediate course of asphalt applied, the contractor will then
finish the concrete repairs along the sidewalks and ADA ramps.
Once complete, the final surface course of asphalt will be applied. Weather dependent and progress of
work, paving is expected to last through October.
The installation of the water main is complete on East Court Street from Main Street to Prospect Street.
Crews will be installing catch basins this week and plan to move to water services and fire lines
beginning Monday. This work is expected to last into September. During this process, access to City Lot
1 will be maintained as much as possible from either Main Street or Prospect Street.
The timeline above is dependent upon progress of work and weather. Questions about this work may be
directed to the engineering division at 419-354-6227.

No posts to display